Japan ports update - 17th March 0730GMT - Wet bulk

There are over 200 commercial ports. Our reports concern only those ports that have been disrupted by the earthquake and Tsunami.

Rescue operations are still being undertaken and no indication yet of repair/recovery works, not only to the ports but to the many roads, bridges etc. destroyed by the quake and tsunami on March 11, 2011.

Akita Open Tohoku Elect Working in normal
Atsumi Open Chubu Elect Working in normal
Chiba Open Cosmo Oil (14-A Pier) Working in normal
Chiba Open Cosmo Oil (Main) To resume vsl cargo operation from 18th / Shore facility operation in suspention / Remaining LPG in collapsed tank to be burnt out in a few more days
Chiba Open Fuji Oil Working in normal
Chiba Open Idemitsu Kosan Working in normal
Chiba Open Keiyo Sea Berth Working in normal
Chiba Open KPI Vsl cargo operation working in normal / Shore facility resumed operation partly / Full operation in a few days
Chiba Open Marubeni Ennex Working in normal
Chiba Open Sumitomo Chem Working in normal
Etajima Open Itochu Enex Working in normal
Imari Open Kyushu LPG Working in normal
Iwakuni Open JXNOE (Marifu) Working in normal
Kanokawa Open Kanokawa Terminal Working in normal
Karatsu Open LGT Working in normal
Kashima Open for aid supply only Kashima Denkai Closed / Unknown when to resume operation
Kashima Open for aid supply only Kashima Kyobi Closed / Unknown when to resume operation
Kashima Open for aid supply only Kashima Oil Closed / Unknown when to resume operation
Kashima Open for aid supply only Mitsubishi Chem Closed / Unknown when to resume operation
Kashima Open for aid supply only Shin-Etsu Chem Closed / Unknown when to resume operation
Kawasaki Open JXNOE (Kawasaki Plant) No damage
Kawasaki Open JXNOE (LPG) Working in normal
Kawasaki Open Keihin Kawasaki Sea Berth Working in normal
Kawasaki Open MC Terminal Working in normal
Kawasaki Open Nippon Vopak Working in normal
Kawasaki Open TGSK Vsl cargo operation working in normal / Shore facility resumed operation partly / Full operation to resume shortly
Kawasaki Open Toa Oil Working in normal
Kawasaki Open Tokyo Yuso Working in normal
Kiire Open NOST Working in normal
Kikuma Open Taiyo Oil Working in normal
Kinoe Open Kinoe Terminal Working in normal
Kinuura Open Showa Shell Sekiyu Working in normal
Kinwan Open Okinawa CTS Working in normal
Kinwan Open Okinawa Idemitsu Working in normal
Kobe Open TM Terminal Working in normal
Mizushima Open JXNOE A Factory Working in normal
Mizushima Open JXNOE B Factory Working in normal
Moji Open Marubeni Ennex Working in normal
Muroran Open JXNOE Working in normal
Mutsure Open Daitoh Tank Terminal Working in normal
Nagoya Open Idemitsu Kosan (Aichi) Working in normal
Nagoya Open Isewan Sea Berth Working in normal
Nagoya Open JXNOE (Chita) Working in normal
Nakagusuku Open Nansei Sekiyu Working in normal
Namikata Open Namikata Terminal Working in normal
Naoshima Open Mitsubishi Materials Working in normal
Niigata Open Tohoku Elect Working in normal
Niihama Open Sumitomo Metal Mining Working in normal
Oita Open JXNOE Working in normal
Oita Open Showa Denko Working in normal
Onahama Open for aid supply only Onahama Petroleum Closed / Unknown when to resume operation
Osaka Open Sakurajima Futo Working in normal
Owase Open Chubu Elect Working in normal
Saganoseki Open Pan Pacific Copper Working in normal
Sakai Open Cosmo Oil Working in normal
Sakai Open Marubeni Ennex Working in normal
Sakai Open Mitsui Chem Working in normal
Sakai Open OIREC (ex JXNOE Osaka) Working in normal
Sakai Open TGSK Working in normal
Sakaide Open Cosmo Oil Working in normal
Sendai Closed / Restoration under process (aid supply only) JXNOE Closed / Unknown when to resume operation
Shimizu Open TGSK Working in normal
Shimotsu Open TGSK  (Wakayama) Working in normal
Tokuyama Open Idemitsu Kosan Working in normal
Tokuyama Open Nippon Seiro Working in normal
Tomakomai Open Idemitsu Kosan Working in normal
Ube Open Seibu Oil Working in normal
Wakayama Open Wakayama Petroleum Refining Working in normal
Yokkaichi Open Cosmo Oil Working in normal
Yokkaichi Open Showa Yokkaichi Sekiyu Working in normal
Yokohama Open ExxonMobil (Tsurumi) Working in normal
Yokohama Open JXNOE (Negishi) To resume operation next week